Client
Société des ponts Jacques-Cartier et Champlain inc.
Location
Beauharnois-Melocheville, Canada
Construction cost
$8,400,000
Year
2001-2003
Work supervision
In 2003, GENIVAR proceeded with the reconditioning of the concrete and lighting of the Southern tube and southern and central ventilation courses of the Melocheville Tunnel. In 2001-2002, the interventions included : reconditioning of the concrete in the Northern and Southern tubes, reconstruction of the northern sidewalk, injection of cracks, concrete work, installation of a temporary electrical system and temporary wrought iron and doors, sandblasting, traffic control, reconditioning of power distribution in the tunnel, lighting and outlets In the galleries.